FAIRFIELD, Calif. — November 17, 2026. Fairfield has adopted an interim 45-day moratorium on new data-center land-use applications. The City Council voted 7–0 on November 10 to approve Ordinance 2026-08, and the temporary restrictions took effect November 11. The initial period is scheduled to end December 25 unless the council follows the required process to extend it.
What is paused?
The ordinance stops the city from accepting, processing or approving new applications and land-use entitlements for data centers while officials study zoning, electricity and water requirements, noise, fire risks and impacts on neighboring communities. City Attorney and planning staff have been asked to prepare a written report before the moratorium expires. A future extension would require another publicly noticed procedure and vote; the current action is not a permanent ban.
Concern over a potential 150-megawatt facility
The issue arose amid community concern about a potential approximately 150 MW data center near Canon Road and North Gate Road, in the northeast of the city. Vallejo Sun reported that officials discussed the possibility of energy infrastructure serving a large industrial area and offering backup power benefits near Travis Air Force Base. Residents argued that large computer facilities can impose significant load on the electric grid and draw on water resources. Speakers also raised questions about backup battery fires and emergency preparedness.
But City Manager David Gassaway told council members that no formal data-center application was pending anywhere in Fairfield at the time of the meeting. A concept under discussion is not an approved construction project or an application already on file.
What comes next?
The city must study whether new standards are needed for setbacks, water supply, noise, grid interconnection and fire suppression, and report on its findings ahead of the expiration deadline. The council may propose permanent zoning rules after the study; no final regulations have been enacted by this moratorium alone.
Sources: Fairfield City Council official November 10 agenda and Ordinance 2026-08; November 10 recorded meeting, unanimous 7–0 vote; Vallejo Sun, November 11, community reaction and proposed project.
Featured photograph: illustrative network equipment by Jordan Harrison / Unsplash, not a Fairfield data center.
Support Fairfield News
Choose how to support Fairfield News:
Credit / Debit Card via StripeChoose your contribution amount on the secure California58 Stripe checkout. One-time support for independent local journalism.
Continue with PayPal Continue with ZelleZelle payments go to Vitaly Ataev Troshin. Please verify the recipient in your bank before sending. Availability depends on your bank.
Optional reader support. When possible, add “Fairfield News” to the payment note. Contributions are not advertised as tax-deductible. Support does not influence editorial decisions.More from Fairfield News
- Fairfield Studies 189-Acre Hill Ranch Annexation With New Food-and-Beverage Industrial Zone, No Warehouses →
- Fairfield Leads Environmental Review of North Bay Water Plant Expansion to 65 Million Gallons Daily →
- Fairfield Weighs $6.42 Million Transit Funding Claim for FAST Buses, ADA Service and Microtransit →
- Fairfield's New ADU Rules Move Toward Council: Three Classes, Condo Options and Updated Fees →
- Man Found Fatally Shot on Clay Bank Road in Fairfield; Detectives Seek Answers →

COMMUNITY
Comments
Join the California58 conversation. You must be signed in to comment.
Create a free California58 account or sign in with an available social provider.